desk awaiting review. Once the team receives word from AJT - 2, they
hope to move forward with deployment at LAX.
o The transmit map for CLT was approved by the Spectrum office on
1/5/2016. There is now a risk that the FCC license proc ess may delay the
installation and deployment of the transponders past 3/1 of this year.
o CLE and MEM are also in the process of receiving Vehicle ADS - B.
D eployment at those sites are currently underway
o Outreach briefings are tentatively scheduled for HOU and IAH in early
February.