Appendix Article 9 - 1
Article 9 PAR forms
PRE ARBITRATION REVIEW (PAR) DECISION
ARTICLE 9, SECTION 8
______________________________________________________________________________________
NATCA Number: NATCA Presenter(s):
FAA Number: FAA Presenter(s):
Date of Meeting: Region:
Parties Accept Neutral Evaluator's Opinion
Parties Do Not Accept Neutral Evaluator's Opinion
Party That Does Not Accept Recommendation
FAA NATCA
Neutral Evaluator Recommendation: (Each party shall sign at the conclusion of each session):
Extension Requested by FAA
Extension Requested by NATCA
For extension, enter date answer due:
Note: Failure to respond by the date answer is due shall constitute a rejection of the Neutral Evaluator's
recommendation.
Neutral Evaluators Signature: ____________________________________________
FAA Accepts Does Not Accept Signed: _____________________________
NATCA Accepts Does Not Accept Signed: _____________________________
The Parties recognize that the party that disagreed with the neutral evaluator's opinion shall incur the
arbitrator's fee and expenses if it does not prevail at the arbitration hearing. The arbitration decision must
be sustained in full or denied in full for the said party to incur the arbitrator's fees and expenses.
Neutral Evaluator's Opinion/Recommendation: