The first phase is moving along rapidly. The first phase r adio updates are complete.
Tuning flights were completed in early April. The second round of contractor flights
tuning flights to addres s ATCRBS performance was conducted in late May. A flight
inspection planning session was held on May 23 at SCT, and the flight inspection to
evaluate the service from an Air Traffic perspective is planned for July 17 - 18.
Operational use of WAM could begi n as early as August 2017.
SAAT has been analyzing Potomac (PCT) Fusion i ssues for potential solutions. The
facility has been struggling with a number of issues related to problem rada r sites or a
lack of coverage. Radar analysis is ongoing, including t he benefit of adding Quantico
radar to PCT.
A long - awaited estimate for adding identified radars to C LE has finally been delivered.
SBS Article 114 agreed to a path forward to add multiple radars to CLE in support of
Fusion.
Met with N90 management and NA TCA representatives to discuss the support n eeded
to transition to Fusion. The facility is targeting a January 2018 start.